Preliminary Evaluation and Pre-Design Reports for Capital Projects

 Project Name 
(Birch Bay Comprehensive Stormwater Plan ID or Subwatershed Master Plan ID)
 Reports  Project Status
Beachway Drive & Fern/Park Stormwater Improvements (CS-2, CS-3)Preliminary Solutions Report
Public Comments Received with Response
Pre-design Report
Preliminary Solutions report completed in 2013. Pre-design report and construction completed in 2014.  
Charel Terrace Stormwater System Improvements (BR-02)        Oertel Drive-Charel Drive-Cary Lane Infrastructure Project - Undersized Conveyance Determination Preliminary Design Memorandum Preliminary design completed August 2010.
Final design completed May 2011.
Construction completed November 2011.
Collaborative Drainage System Repair on Birch Point (BR-03)    Stormwater Site Plan
Preliminary Engineer's Report
Stormwater study with preliminary design options completed 2015.  Final design completed in 2016.  Construction scheduled for late 2016.
Cottonwood Neighborhood Drainage Improvements (CT-06 A & B, CN-1)   Preliminary design completed April 2010.
Final design fall 2012.
Construction completed November 2013.
Cottonwood Drive Drainage Improvements (HL-2, HL-3)   Preliminary Solutions Report
Public Comments Received with Response
Pre-design Report 
On the 6-year Water Resources Improvement Program list.
Preliminary Solutions and Pre-design Reports completed in 2014.  
Cottonwood Beach Central Drainage Improvements (North Bay Trailer Park area) (CS-4) Preliminary Solutions Report
Public Comments Received with Response
Pre-design Report
Preliminary Solutions and Pre-design Reports completed in 2014.  
Hogan Drive Outlet Maintenance and Repair
(BR-05B)
Hogan Drive Alternatives Memorandum  Corrective maintenance construction completed October 2012.
Normar Place
(BR-05)
Normar Place Drainage Problem and Solution Summary Memorandum  Not currently on the 6-year Water Resources Improvement Program list.
Richmond Park Drainage Improvements 
(CT-01 Shintaffer at Richmond Park)
Shintaffer Road at Richmond Park Conveyance Issue and Solution Summary Memorandum 

Evaluation of Richmond Park Drainage Improvement Design Options
On the 6-year Water Resources Improvement Program list.
Roger's Slough Drainage Improvements
(BV-01)
Roger's Slough Preliminary Concept Designs

 
Tide gate operation and channel management improvements have reduced flooding instances and are more cost effective than capital solutions.
Semiahmoo Drive Cross-Culvert Drainage Improvements (BR-11)   Corrective maintenance completed October 2010.
Terrell Creek Water Quality Improvements
(CC-05, SP-03)
Terrell Creek Water Quality Problem and Solution Summary Memorandum
Figure 1
Figure 2 
Engineer's recommendation to consider a habitat restoration project instead of a CIP.  
Wooldridge Neighborhood Drainage Improvements
(CC-03)
Wooldridge Avenue Yard Flooding and Solution Summary Memorandum 
Figure 3: Existing Site Plan
Preliminary Solutions Report
Public Comments Received with Response
Pre-design Report
Preliminary Solutions and Pre-design Reports completed in 2014.  
On the 6-year Water Resources Improvement Program list.